Activity 7

Learning Goal: I’m working on a business question and need guidance to help me learn.

Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:

Activity Description Predecessors Duration (Days)
A Site selection None 4
B Buy concessions A 4
C Rent facilities A 2
D Build stands A 5
E Generator & wiring installation C 2
F Security B. 4
G Lighting installation E 2
H Sound system installation E, F 2
I Stage construction D 3
J Tear down G, H, I 4
  1. Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
  2. Identify all paths through the network. Which is the critical path?
  3. Which activities have slack time?
  4. Identify all burst activities and merge activities.
Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.